93 Fast Bridge Replacement System Now Being Utilized Throughout US

Aug 15, 2018 | Case Studies

This historic project replaced fourteen bridges in Medford over the course of just ten weekends between June and August, 2011. MassDOT used several innovations, a detailed traffic management plan and a comprehensive communications plan to complete the bridge work safely, efficiently, economically, and in a manner that caused the least possible construction-related impacts and congestion. The project was completed on-budget and ahead of schedule, replacing all fourteen bridges in less than a year. Using conventional methods, this project would have taken at least four years, and during those four years drivers would have had to endure long-term lane closure.

Project Team

GEI Engineering – Design and Management
J. F White – Construction
W.L. French – Demolition and Transportation